$538.5 million construction contract awarded on the Sydney Metro – Western Sydney Airport project

Details have been revealed about a major contract on the Sydney Metro – Western Sydney Airport project.

CPB Contractors and United Infrastructure will deliver about 10.4 kilometres of surface and civil alignment works as part of the $538.5 million construction contract.

The contract includes:

  • 3.5 kilometres of elevated viaduct at Orchard Hills and Luddenham
  • 6.7 kilometres of earthworks for track formation
  • A 190 metre long rail bridge over the new M12 motorway
  • A 20 metre long rail bridge within the airport
  • Temporary and permanent access roads
  • Bulk earthworks for the stabling and maintenance facility site.

At least 20 per cent of the contract workforce will be from Greater Western Sydney.

In December a $1.8 billion contract was awarded to CPB Contractors and Ghella to build the new twin metro rail tunnels.

The third and final major contract package to be procured for the project is expected to be awarded at the end of this year.

The Sydney Metro – Western Sydney Airport project will support 14,000 jobs and is jointly funded by the Australian and NSW governments.