BAM completes successful TransPennine blockade

Railway passengers in Greater Manchester moved one step closer to faster, more frequent, and more reliable trains this weekend after major railway upgrades were completed on time between Manchester Victoria, Rochdale and Stalybridge as part of the multi -billion-pound Transpennine Route Upgrade.

As the civil engineering lead for the works, BAM Nuttall took a major role in delivering the programme that took place from Saturday 31 July to Monday 16 August. Two railway bridges at Dantzic Street and Queens Road were completely reconstructed and two bridges at Bromley Street and Oldham Road were strengthened and waterproofed.

Alongside this over 3000m of track was upgraded, track was remodelled between Manchester Victoria and Stalybridge and 17 new signals were also installed.

Advertisement

This blockade was just the beginning for the 76-mile Transpennine Route Upgrade that will deliver a high performing, reliable railway for passengers with more seats, more trains and faster journeys between Manchester and York via Huddersfield and Leeds.

Brian Walton, Deputy Alliance Director, said: “I would like to pass on my thanks and congratulations to the whole BAM team for the massive effort that has gone into ensuring that the Alliance’s first extended railway closure has been a safe and successful one.

“The success of the work has without question only been made possible by the collaboration of all those involved from the early development stages, through the planning phases over the last 24 months and the execution of the works itself. Delivering all these complex works and handing back on time was always going to be critical in helping to build the reputation of BAM and the TRU West Alliance and that is exactly what has been achieved.”

Neil Holm, Transpennine Route Upgrade Director for Network Rail, said: “We’ve made major progress across Greater Manchester on this key part of the Transpennine Route Upgrade. Our teams have worked around the clock over the past 16 days to improve journeys for passengers.

“As well as bringing more reliable services, this complex upgrade will eventually allow more trains and faster trains to run on the busy route between Manchester and York.”

image_pdfDownload article

Most Popular

Government approves £48 million of funding for transformation of Peterborough’s Station Quarter

A total of £48 million is on its way to Peterborough, following a successful Levelling Up Fund bid for the first phase of regeneration...

Former easyJet executive switches planes for trains

Northern has appointed John Khatri as its head of engineering transformation delivery. The former easyJet executive, who has also held a number of senior roles...

Kier appoints Louisa Finlay as Chief People Officer

Kier Group plc has announced that Louisa Finlay, currently Kier Construction’s Clients and Markets Managing Director, has been appointed as Chief People Officer and...

Show-stopper guest for Severn Valley Railway’s Spring Steam Gala

The Severn Valley Railway has released the name of the show-stopping guest locomotive that it has secured for its Spring Steam Gala. The iconic...
- Advertisement -