Engineers to replace track at Lowestoft station

Engineers are preparing to replace 50-year-old track in platforms 2 and 3 at Lowestoft station.

Network Rail said that the ground beneath the rails was currently saturated in several places along the platforms, affecting the condition of the track and increasing the likelihood of faults that could lead to disruption. Oil from previous generations of trains is also visible.

The infrastructure manager said engineers would use a specialist vacuum machine to remove areas of old ballast, before replacing it with fresh material. Sleepers and rails will also be replaced at various locations within the platforms.

The work will take place between Friday 13 – Monday 16 November inclusive, with train services affected on both the Lowestoft-Norwich and Lowestoft-Ipswich lines as follows:

Buses replace trains between:

  • Lowestoft and Norwich
  • Lowestoft and Oulton Broad South
  • Lowestoft and Haddiscoe (Friday and Monday only)
  • Reedham and Lingwood via Cantley

Trains will continue to operate between Ipswich and Oulton Broad South, and between Norwich and Great Yarmouth.

Passengers should check before they travel at greateranglia.co.uk

Joe Kennedy, Infrastructure Director working as part of GBR Anglia, said: “The vital work we’re doing in November will help us provide the best possible service on these busy and important routes for years to come. We’re really sorry for the disruption, especially on the two weekdays, but this is a big job that we must get done to maintain a reliable railway.”

GBR Anglia brings c2c, Greater Anglia and Network Rail Anglia together under a single unified structure on the journey to Great British Railways. The three organisations are increasingly planning and delivering as one railway.