Home Infrastructure Polystyrene platforms bridge gap for Manchester Piccadilly project

Polystyrene platforms bridge gap for Manchester Piccadilly project

Polystyrene blocks have been used by Network Rail to bridge the gaps between platforms to build a temporary route along the width of Manchester Piccadilly railway station so that mobile elevated working platforms (MEWPs) could reach the roof structure.

Twelve ‘splice plates’ – which join the bottom chords of the steel trusses – are being replaced. They have been specially designed in keeping with the heritage features of the building.

It is part of the strengthening work to the Victorian-built train shed’s gable end which began over Christmas. No trains will be running on Sunday 15 January as the 25,000-volt overhead lines which usually power trains need to be switched off for engineers to work at height.

Advertisement

Manchester Piccadilly’s station concourse and retail units will stay open, but passengers will be directed to the buses on Station Approach to complete their journeys.

People are advised to allow extra time for their journeys and check National Rail Enquiries at www.nationalrail.co.uk or with their individual train operator* before they travel.

Kara Wood, Network Rail’s North West head of performance and customer relationship, said: “We’ve been carrying out a lot of essential work to improve Manchester Piccadilly station over Christmas and New Year and this weekend the teams are coming back to complete the second phase of roof maintenance.

“Because we have to turn the power lines off to safely carry out the structural work it means we can’t run any trains all day on Sunday. I’d like to thank passengers in advance for their patience while we keep people on the move with rail replacement buses and urge people to check National Rail Enquiries so they know how it will impact on their journey.”

Meanwhile further railway upgrades in Greater Manchester will also see changes to journeys in the coming weeks.

On 15 January and 22 January, resurfacing works will be taking place on platforms 13 & 14 and tactile studs are being installed to make it safer for blind and partially sighted people.

Both platforms will be closed to trains to complete the resurfacing work which started over the Christmas break.

Then upgrades on the Manchester Airport line which started last weekend will continue on Sundays in January and February.

Three stations (Mauldeth Road, East Didsbury and Gatley) are having platforms extended to allow for longer trains to call there in the future.

Photo credit: Network Rail

image_pdfDownload article

Most Popular

DRS takes delivery of 25 new JNA-Z box wagons from VTG Rail UK

Direct Rail Services (DRS) has taken delivery of a fleet of 25 brand new JNA-Z box wagons from VTG Rail UK, the country’s leading...

SYSTRA employee named one of Planner Magazine’s Women of Influence 2024

The Planner Magazine has selected Jenny Jefferies, Technical Expert - Consents at SYSTRA, as one of its Women of Influence for 2024. Jenny, who is...

ORR review leads to 50 per cent reduction in maximum fees for ticket refunds

The Office of Rail and Road (ORR) has announced that, thanks to new rules, the maximum fee that train operators and ticket retailers can...

East West Rail to hold drop-in events ahead of statutory consultation

East West Railway Company (EWR) will hold a series of information events in May, helping people to understand how the formal application process to...
- Advertisement -