See the video as railway underbridges installed in four-day operation

A race against time to complete a massive and complex engineering project to improve rail links and help people and traffic move more easily around Bicester has been completed on schedule.

After three years of planning, teams from Oxfordshire County Council, Cherwell District Council and Network Rail fitted two new railway underpasses on the Chiltern main line during a 100-hour window over the Easter period. If the project had not met its deadline, the organisations would have had to wait another five to 10 years for the next opportunity to carry out to work, due to the heavy demands on the Network Rail calendar.

Owen Jenkins, Oxfordshire County Council’s Director of Growth and Economy, said: “This successful operation was due to the extraordinary cooperation between the councils and Network Rail and its contractors. It is a testament to the hard work over the four days when the underbridges were put in place, as well as the high level of planning and collaborative work in the three years beforehand, covering the conception, design and pre-construction phases.”

Advertisement

The underbridges were inserted underneath the Marylebone/Aynho line north-west of Bicester between 2 – 5 April, during the East bank holiday weekend. The structures had been built off-site between October 2020 and March 2021, ready to be installed.

The railway line was closed to allow for 21,000 tonnes of earth to be moved to make way for the underpasses. The teams removed and replaced 400 metres of railway track, and then drove the two new underpasses under the railway bridge with a huge transporter.

Dave Penney, Network Rail’s Central Route Director, said: “This £12.3 million investment in Bicester to create two new routes under the railway will not only benefit the flow of people and traffic, but also help both council’s regeneration vision. It’s a great example of how the rail industry can work in partnership with local authorities to unlock opportunities and growth for communities.”

The new structures will connect areas of the garden town, which were previously cut off from each other by the railway line, and help open up the Eco-Town area of Bicester, including enabling the creation of up to 6,000 new homes and new community and recreational facilities. The steel underbridge will accommodate the planned realignment of the A4095, while the underpass will connect the new development for cyclists and pedestrians.

Robert Jolley, Assistant Director for Growth and Economy at Cherwell District Council, said: “This has been a key project for the development of Bicester Garden Town, and is an extraordinary example of multi-agency working bringing significant key players together with a clear, common purpose. It has also involved the productive use of both the growth deal and other funding, to deliver large-scale positive changes for our communities.

“Working with partners, we have unlocked important land to the north-west of Bicester, creating accessible walking and cycling routes for our future residents to enjoy.”

The project, which was on time and on budget while sticking to a strict COVID-19 risk strategy, provides upgraded rail track which will improve future journeys between London Marylebone and the Midlands. The work also involved the county council’s specialist consultant Stantec, Network Rail’s framework contractor Story Ltd and Homes England.

Photo and video credit: Oxfordshire County Council

image_pdfDownload article

Most Popular

DRS takes delivery of 25 new JNA-Z box wagons from VTG Rail UK

Direct Rail Services (DRS) has taken delivery of a fleet of 25 brand new JNA-Z box wagons from VTG Rail UK, the country’s leading...

SYSTRA employee named one of Planner Magazine’s Women of Influence 2024

The Planner Magazine has selected Jenny Jefferies, Technical Expert - Consents at SYSTRA, as one of its Women of Influence for 2024. Jenny, who is...

ORR review leads to 50 per cent reduction in maximum fees for ticket refunds

The Office of Rail and Road (ORR) has announced that, thanks to new rules, the maximum fee that train operators and ticket retailers can...

East West Rail to hold drop-in events ahead of statutory consultation

East West Railway Company (EWR) will hold a series of information events in May, helping people to understand how the formal application process to...
- Advertisement -