Signalling specialist helps to address level crossing issues in Northumberland

A Sutton Coldfield-based signalling specialist has helped to address ongoing issues with a level crossing on the East Coast Main Line (ECML).

DigiSig Rail supported engineering works at Christon Bank Level Crossing, located on the ECML in Northumberland. The project was commissioned on August 18, 2024.

The Christon Bank Level Crossing, controlled by the Alnmouth Signal Box, had been facing timing issues with LNER Class 80X trains on the Down Main Line. These problems were due to trains being shown a yellow aspect at signal A145, upon approaching the crossing. As a result, the level crossing barriers were not lowered in time, causing the protecting signal to remain at a yellow aspect. This had a significant impact on train performance and operational efficiency.

The team at DigiSig Rail were tasked with addressing these issues. The scope of works included scheme development to approval in principle (AIP) and detailed design to delivery, which encompassed signalling design, timing reports, and alterations to the SSI Data & Control Tables for the Christon Bank Level Crossing.

During the development phase, the team carried out base plan surveys and repositioned the existing strike-in points. This adjustment ensured adequate time for the automatic lowering of the crossing barriers, allowing signal A145 to display a clear, unrestricted aspect. The team also produced a Timing Investigation Report, which identified the primary cause of the issue. Additionally, a Reasonable Opportunity Report was developed to evaluate the potential for similar problems on the Up Main Line.

Following AIP, the detailed design stage involved amending the Control Tables & SSI data to resolve the signalling issues.

A DigiSig spokesperson said that the successful completion of the project clearly demonstrated the company’s commitment to designing and delivering high-quality signalling design solutions which enhance railway safety and performance.

Steven Rudland – Performance Hub Manager at LNER, commented: “I am now witnessing the trickle of (smiling!) drivers popping into the office to say they have gone through greens here at 125mph for the first time!”

Alison Rawson – Principal Project Manager at Mosaic Rail added: “DigiSig Rail produced both ES4 & ES5 designs for the Christon Bank Project to a high standard and met with all the specific programme requirements.”