Transport for Wales: Some Class 175s need further repairs to the engines

Transport for Wales has temporarily withdrawn a number of its Class 175 trains to allow additional maintenance checks to be carried out following some recent mechanical issues. 

These maintenance checks have found that some of the trains need further repairs to the engines before they come back into passenger service.

As a result, disruption to passenger services is likely to continue into early April.

Advertisement

Disruption is likely across the Wales and Borders network, not just on those routes served by the Class 175s, as trains are moved to provide capacity where demand is highest. Customers are asked to check before they travel. This includes first and last trains and any ferry connections to ensure sufficient time is allowed.

Routes affected by the changes are:

  • Newport – Crosskeys – service cancelled (no rail replacement).
  • Chester-Liverpool – service cancelled (Merseyrail ticket acceptance).
  • Conwy Valley Line – service cancelled (rail replacement).
  • Wrexham-Bidston Line – service cancelled with rail replacement buses.
  • Cambrian Coast – early morning Barmouth service cancelled, with rail replacement buses.
  • Core Valley Lines – reduced service on some routes. No services between Pontypridd and Merthyr Tydfil until Monday 3 April due to transformation work for the South Wales Metro.
  • West Wales lines – rail services have resumed.
  • Milford Haven and Fishguard services west of Carmarthen – rail services have resumed.

Jan Chaudhry-Van der Velde, Chief Operations Officer at TfW, said: “The safety of our customers and colleagues remains our top priority.

“Our Class 175 trains will not be allowed into passenger service again until each train has had its engines checked and repaired, and has passed the relevant safety inspections. This programme of work is happening as we speak, at Chester depot, where these trains are maintained on our behalf by CAF Rail UK. 

“An initial supply of materials is available for the repair programme, and further parts are being sourced from overseas to speed up the process. The position will improve each week, and the completion of the repair programme is expected to go into April.

“Whilst this leaves us with a temporary shortage of rolling stock, other fleets are being spread out across the Wales and Borders network, and timetables have been adjusted to try and impact the fewest number of passengers.

“We’re very sorry for the disruption to customers’ journeys while we carry out this essential work.”

Photo credit: Transport for Wales

image_pdfDownload article

Most Popular

Nuclear Transport Solutions launches major recruitment drive

Nuclear Transport Solutions (NTS) has launched a major nationwide recruitment drive in a bid to strengthen and support its existing teams.

Serco announces new appointments to the Group Executive Committee

Serco Group Plc, a leading international provider of services to governments, announces the appointment of Gillian Duggan as Chief People and Culture Officer, and the appointment of Ruth McGowan to the new role of Chief Strategy and Growth Officer.

Second phase of significant upgrades at Morley approaches

Nine days of major upgrades are due to take place from 17-25 June at Morley station as part of the Transpennine Route Upgrade. Over nine...

HS2 launches new construction apprenticeships

Jobseekers and career changers who want to work in construction are encouraged to register for a new two-week pre-employment programme that could lead to...
- Advertisement -