ORR releases its review on how industry responded to Hitachi class 800 withdrawal

The Office of Rail and Road (ORR) has made recommendations after reviewing the industry’s response to potential safety issues leading to the withdrawal of Hitachi Rail’s Class 800 series trains in May last year.

It added Hitachi Rail and its industry partners are set to carry out repairs on 1,247 Class 800 series vehicles and a further 487 Class 385 and 395 vehicles.

The action to withdraw the class 800 trains was taken after some were found to have cracks on their bodyshell. There were cracks found around yaw damper brackets and, later, around where lifting plates attach to the body.

In the review, ORR reflects that more work is needed by the industry to help understand the reasons for higher levels of fatigue loading experienced by the rolling stock. After some analysis, it was found the trains experienced greater loads from train movement than allowed for in the original design, and this damaged the area around the yaw damper brackets.

The Hitachi Rail design, ORR emphasises, complied with the applicable industry standards.

ORR also asked Hitachi Rail to formally review welding processes for challenging component geometry.

It said that designers of rolling stock should understand the risk posed by stress corrosion cracking – specifically with regards to 7000 series aluminium, which was used on the trains. It says characteristics of this specific aluminium alloy, when combined with built-in stresses from being welded to the body and exposure to air containing chloride, resulted in this type of cracking on the train’s lifting plates area.

Furthermore, ORR queries in its review whether industry should have a standard for mitigating this type of damage.

It adds the industry should develop a process for responding to issues such as this, overseen by a strong independent chair.

The response of the industry

The review says that when cracks were found on the bodyshell (yaw damper bracket and anti-roll bar fixing points) of some trains in spring 2021, rigorous safety checks by Hitachi Rail and the train operators impacted were carried out, with oversight from ORR.

Stringent mitigation measures were put in place to allow the trains to re-enter service without passenger safety being compromised, which have assured no safety failures and trains have performed as specified while in service.

ORR immediately launched a review of both the passenger and safety impact after trains were withdrawn from service for safety checks on Great Western Railway, London North Eastern Railway, TransPennine Express and Hull Trains, along with cracks being separately discovered after examination on ScotRail’s Class 385 and Southeastern’s Class 395 trains.

Rail engineers from the manufacturer, Hitachi Rail, and independent experts have also completed rigorous analysis to gain a clearer understanding of the issue.

ORR review

ORR’s review concluded that on the vehicle body in the area above the wheels close to the yaw damper bracket and anti-roll bar fixing points, fatigue cracking was caused by the trains experiencing greater loads from train movement than allowed for in the original design. It is not yet known for certain why this happened, although potential factors include wheel wear and track design.

Image supplied by ORR

Additional cracks found in the area where the lifting plates attach to the vehicle body were the result of stress corrosion cracking, resulting from the use of the particular type of 7000 series aluminium in various areas of the Hitachi Rail Class 800 series.

The characteristics of the specific aluminium alloy in combination with built-in stresses from being welded to the body and exposure to air containing chloride resulted in cracking.

ORR recommendations in detail

To ensure further safety improvements, ORR is recommending that:

  • The industry should conduct further work to identify the reasons for the higher levels of fatigue loading experienced by rolling stock. Since the Hitachi Rail design complied with the applicable industry standards, the industry as a whole should evaluate whether the applicable standards take into account the loads arising from operation on the rail network in Great Britain. This industry collaboration will require the involvement of those parties responsible for design, manufacture and maintenance of rolling stock including, but not limited to, Hitachi Rail.
  • Hitachi Rail should carry out a formal review of the effectiveness of their processes for welding when the component geometry is more challenging, which should include consideration of whether the existing approach adequately mitigates the risks of a weld with insufficient fusion being accepted.
  • Designers of rolling stock should understand the risk posed by stress corrosion cracking and give it specific consideration when proposing the use of 7000 series aluminium components. This does not mean that the specific type of aluminium should not be used in future, or that the aluminium used in the current trains compromises safety; but when used, steps should be taken to ensure protection of structures.
  • The industry should consider whether a standard for mitigating stress corrosion cracking risk should be developed, as no dedicated standard currently exists.
  • The industry should develop a process for responding to similar future cross-industry crisis events and appoint a strong, independent chair who can maintain pace, focus and ensure all voices are heard.

In addition to conducting its review, ORR has continued to carry out oversight to ensure robust processes are being followed.

Hitachi Rail and its industry partners are about to start the major programme of work to repair 1,247 Class 800 series vehicles and a further 487 Class 385 and 395 vehicles.

ORR is working with Hitachi Rail and its partners to agree the permanent solution to address the issues. Hitachi Rail plans to replace the affected part of the original body structure, including the longitudinal welds where the fatigue cracks have occurred, and the mounting brackets. Hitachi Rail has also proposed to modify the addition of bolts to retain the plate in the unlikely event that the welds fail completely as a result of the stress corrosion cracking.

It is proposed that this programme is expected to take place over the next six years in order to minimise disruption to passengers while ensuring safety, with the minimum number of units out of service at any one time.

ORR’s review states that Hitachi Rail is prioritising the trains for repair on the basis of need, drawing on the monitoring data it has compiled from the fleet engineering and safety checks.

ORR will continue its oversight and follow the industry’s actions as well as promote the lessons learned in operators’ safety management systems to continue to deliver improvements. The industry has established processes for improving standards and ORR expects that these will be followed promptly.

The regulator praised the rapid industry response and subsequent work to safely reintroduce trains to service.

ORR’s HM Chief Inspector of Railways Ian Prosser CBE said: “With our oversight, Hitachi Rail and operators have put in place robust plans to make sure the right safety issues are being managed following the initial discovery of cracks on the trains, which have allowed trains to re-enter service.

“Safety remains the number one priority. Our review provides a clearer picture of the issue and we will continue our oversight to ensure work moves forward to agree the permanent solution and our recommendations are acted on.

“It is important that the whole industry works together to learn lessons from what has happened and our recommendations will help with that.”

A Hitachi Rail spokesperson said: “The ORR’s report identifies that all Hitachi trains meet relevant standards and that we took the appropriate action to prioritise safety and maintain train availability.

“The report also provides a detailed account of the tireless work to simultaneously keep trains running safely, while working towards the long-term solutions.

“The proposed engineering solutions outlined in the report are currently being reviewed by all partners. We are working together to finalise the plan for their implementation, while always prioritising safety and train availability to support consistent passenger services.”